To enable both our existing customers and potential new clients to plan ahead accordingly, we can advise that the current approximate lead times are in place for the various utility companies:

• Gas – 4 to 8 Weeks to obtain a quotation. Lead time for works to commence is 8 weeks from acceptance of their quotation.

• Electricity – 8 to 12 Weeks to obtain a quotation. Lead time for works to commence is 8 weeks from acceptance of their quotation.

• Water – 8 to 12 Weeks to obtain a quotation. Lead time for works to commence is 8 weeks from acceptance of their quotation.

• BT – BT will ensure service is available for the date of first occupancy.